Commercial cleaning robot trials
Use a controlled zone with a fixed surface, starting soil and cleaning criterion. Log machine operation, refilling and manual rework separately. Preserve the area definition and site photos.
Acceptance checks
Distinct accepted floor area
Count each inspected and accepted patch once. Divide by the full planned area, not by the area the robot attempted.
02Matched soil samples
On an approved off-hours test area, match surface, soil and inspection method. Never give the second method an already cleaned patch.
03Manual work along edges
Log missed edge patches and manual touch-up minutes separately. A patch finished by staff is not robot-only work.
04Effective shift rate
Divide final accepted area by total elapsed shift time including waits, water service and rework, not brush-on time alone.
05Water service provision
Confirm refill, drainage and site connections in scope. A charging dock alone does not establish automatic water service.
06Passage versus scrubbing width
Compare approved machine clearance with the clear door opening on the drawing. Brush width alone gives neither body width nor turning clearance.
07Floor reopening decision
Separate cleaning completion from reopening. The site lead checks residual water and warning-removal criteria under the site procedure; do not test with pedestrians.
08Comparable consumable use
Normalize consumables by accepted area under matched soil conditions. Identify concentrate versus diluted solution before comparing volumes.